The new mobile production plant of Max Bögl Wind in Huai Bong has around 200 employees. Most of these are Thai workers, who are working six days a week in three shifts per day. The goal is to produce three hybrid towers a week for the Korat Wind Farm. In the middle of August 2017, Max Bögl began shipping an entire prefabricated construction plant from Sengenthal to Huai Bong via Nuremberg and Rotterdam. Max Bögl will continue to use mobile production plants for international projects in the future. A mobile manufacturing plant is built at the wind turbine site itself and used to produce concrete elements with local materials and labour.