Siemens will supply 65 SWT-2.3-108 wind turbines and 67 transformers for the Amazon Wind Farm (Fowler Ridge). The customer for this onshore project in Indiana is Pattern Energy.
With a capacity of 150MW, the wind power plant will provide Amazon Web Services’ data center with eco-friendly electricity. Installation is scheduled to begin in July. Commissioning is planned for the first quarter of 2016. Siemens will also be providing long-term service for the wind turbines. In addition to the wind turbines, the associated service and delivery of transformers, Siemens Financial Services (SFS) will also be providing US$ 150 million of construction financing for Fowler Ridge. The nacelles for this project will be assembled in Hutchinson, Kansas. Rotor blades for the turbines are manufactured in Fort Madison, Iowa. The Mount Generation Step up (GSU) transformers for the project are produced in the Siemens plant located in Jackson, Mississippi.