Acciona Energía will build its second wind farm in Texas, the company’s ninth in the USA, which will increase Acciona’s US wind power capacity to 866MW.
An investment of around US$ 200 million, Palmas Altas will have a capacity of 144.9MW and be equipped with 46 AW125/3150 Nordex wind turbines. Grid connection is planned for November 2019. The energy produced by the wind farm will be sold in the ERCOT-South Texas wholesale market.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.