Dominion Energy filed with Virginia's State Corporation Commission (SCC) for approval to build the two 6MW turbines and grid infrastructure needed to connect the facility to the coast. Ørsted, hired by Dominion Energy to build the Coastal Virginia Offshore Wind Project (CVOW), announced that a research vessel will conduct the final ocean floor mapping needed before construction can begin.
The offshore wind project will be located about 27 miles off the coast of Virginia Beach on 2,135 acres of federal waters leased by the Virginia Department of Mines, Minerals and Energy. The two six-megawatt turbines will sit in about 80 feet of water and rise over 550 feet above the ocean's surface. The US$ 300 million project will be funded through existing base rates, enabled by the Grid Transformation & Security Act. Contingent on various regulatory approvals, onshore construction would start in 2019, followed by turbine installation and operation in 2020.