Latest Issue
 
Windtech International September October 2024 issue

 

FOLLOW US AT

follow

 

follow


Enerpac Synchoist for offshore wind gravity bases positioningA synchoist load positioning system, from Enerpac Heavy Lifting Technology, has been used by Finnish wind power production company, Suomen Hyötytuuli Oy, for the installation of gravity base foundations at the Tahkoluoto Offshore Wind Farm, Pori, Finland. The Tahkoluoto Wind Farm is the world’s first offshore windfarm designed for operation in ice conditions.

Operated by Suomen Hyötytuuli Oy, the Tahkoluoto Offshore Wind Farm includes 10 offshore wind turbines, each with a capacity of 4.2MW. Following preparation of the seabed to provide a level surface, the hollow gravity base foundations weighing up to 500 tonnes were installed. During lowering through the splash-zone and positioning on the seabed, the Synchoist system was used below the crane hook to ensure the foundation remained as close to vertical as possible. This prevented damage to the levelled seabed surface and facilitated the subsequent addition of the turbine tower.

To handle the foundation lift without distorting the transition piece flange used to connect the turbine tower, an X-frame lifting tool was developed that connected to the flange. It comprised a lifting frame with four SyncHoist, self-contained PLC-controlled, double acting, push-pull hydraulic cylinders at each corner, and diesel hydraulic powerpack with battery back-up.

High precision manoeuvring of the foundation by the Synchoist system was performed wirelessly by an operator working alongside the foundation installation team. This allowed the operator to lift and lower each cylinder independently to balance, tilt and position the load in response to feedback from four levelling sensors on the foundation.

During installation, the level of the foundation was measured, and where necessary adjusted, at every stage of the lift. At the quayside before the lift – this was to establish the centre of gravity for each foundation, on the vessel, just above the water, 3-4 m into the splash-zone, and 5 cm above the foundation.

 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.