Latest Issue
 
Windtech International November December 2024 issue

 

FOLLOW US AT

follow

 

follow


Offshore Marine Management (OMM) has completed a contract with Fluor for the installation of 36 inter-array cables at the Greater Gabbard wind farm.

Originally contracted to install 29 cables, the remit of OMM’s work was expanded during the course of the project to encompass provision of a full range of installation services for 36 inter-array cables, including front end pre-engineering support, installation and the delivery of a final report using in-house survey capabilities.  Work was completed using the 122m vessel Deep Cygnus. Greater Gabbard is a 504MW offshore wind farm, located 25 kilometres off the Suffolk coast.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.