Latest Issue
 
Windtech International September October 2024 issue

 

FOLLOW US AT

follow

 

follow


On behalf of Erste Group, TÜV SÜD has carried out a technical due diligence study for the funding of a 36MW wind-energy project in North Macedonia. The new wind farm will be built 50 kilometres south-east of Skopje, the capital of North Macedonia, near the village of Bogoslovec.
 
Siemens Gamesa will install eight wind-energy turbines with a hub height of 102.5 metres and rotor diameter of 145 metres on the site. Completion of the wind farm is slated for 2023. The wind farm will have a total installed capacity of 36 MW and will be North Macedonia’s second wind-farm project.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.