Multibrid successfully completed the erecting of two further Multibrid
M5000 offshore wind turbines in Bremerhaven.
The erecting was completed in two
days for the first wind turbine, and in three days for the second wind turbine.
The assembly of the M5000 housings and rotors on the circa 130 meter high towers
went smoothly. The turbines will be connected to an electrical power supply by
the end of June.