Vestas has won an undisclosed order for an 88 MW wind park in Greece with a 20-year service agreement. For this order, Vestas has developed a solution that includes the supply and installation of 21 V136-4.2 MW turbines equipped with Vestas Anti-Icing System.
Turbine delivery is planned for the second quarter of 2020, whilst commissioning is planned for the second half of the same year.
Further Volterra has placed a 54 MW order for 15 V117-3.45 MW wind turbines delivered in 3.6 MW Power Optimised Mode for two wind parks in the Viotia region. The order includes both the Kastro-Likovouni wind park derived from Greece’s feed-in premium system and the Ampelia wind park awarded at the country’s second renewables auction held in December 2018. The order includes supply and installation of the turbines as well as a 20-year service agreement. Turbine delivery is planned for the second and third quarter of 2020, whilst commissioning is planned for the second half of 2020.