Vestas Eólica has received an order for 21 units of the V90-1.8MW wind turbine for the project Caldereros in Castilla-La Mancha, Spain.
The order comprises supply, installation, commissioning, VestasOnline Business SCADA system as well as a service contract for five years. The order has been placed by Enel Unión Fenosa Renovables (EUFER).
Vestas Canada has received an order for 18 units of the V82-1.65MW turbine for three projects near Lake Erie in the province of Ontario, Canada. This is the second order placed by AIM PowerGen under Ontario Power Authority's Standard Offer Program. The order comprises of delivery, commissioning and a two-year service and maintenance agreement. The 18 units of the V82-1.65MW turbine will be installed at three project sites. Each site will comprise of six turbines with a total installed capacity of 9.9MW. Delivery is scheduled for the fall of 2008 and commissioning is expected to be completed in December 2008.
Vestas Benelux has received an order for delivery of 21 units of the V90-3.0MW turbine. The order has been awarded by the Dutch consortium Growind, consisting of 21 private investors. The contract includes delivery, installation, commissioning, Vestas Turbine Watch - Condition Monitoring, the VestasOnline Business SCADA system as well as a service agreement for 10 years. The project will be located near the port of Eemshaven in the very northern part of the province of Groningen in the Netherlands. With a total installed capacity of 63MW. Delivery of the turbines will start at the end 2007, and the wind power plant will be completed during the second quarter of 2008.
Vestas Canada has received an order for 18 units of the V82-1.65MW turbine for three projects near Lake Erie in the province of Ontario, Canada. This is the second order placed by AIM PowerGen under Ontario Power Authority's Standard Offer Program. The order comprises of delivery, commissioning and a two-year service and maintenance agreement. The 18 units of the V82-1.65MW turbine will be installed at three project sites. Each site will comprise of six turbines with a total installed capacity of 9.9MW. Delivery is scheduled for the fall of 2008 and commissioning is expected to be completed in December 2008.
Vestas Benelux has received an order for delivery of 21 units of the V90-3.0MW turbine. The order has been awarded by the Dutch consortium Growind, consisting of 21 private investors. The contract includes delivery, installation, commissioning, Vestas Turbine Watch - Condition Monitoring, the VestasOnline Business SCADA system as well as a service agreement for 10 years. The project will be located near the port of Eemshaven in the very northern part of the province of Groningen in the Netherlands. With a total installed capacity of 63MW. Delivery of the turbines will start at the end 2007, and the wind power plant will be completed during the second quarter of 2008.