Borssele III & IV offshore wind farm has reached full commissioning. The 731.5MW wind farm is located 22 kilometres off the Dutch coast and consists of 77 turbines.
As the Balance of Plant contractor for the Borssele III & IV offshore wind farm, Van Oord was responsible for the design, engineering, procurement, construction and installation of the foundations and inter array cables together with the installation of 77 turbines. Cable installation vessel Nexus and trencher Dig-It completed the installation and burial of more than 170 kilometres of inter array cables.