enXco, an EDF Energies Nouvelles Company, and KCP&L have entered into a Power Purchase Agreement (PPA) for a 100.8MW wind energy facility to be built in Ford County, Kansas, 17 miles northeast of Dodge City, USA.
The agreement was finalised in November 2011. enXco will develop, build, and own the Spearville 3 Wind Project, consisting of 63 GE XLE turbines, while KCP&L will buy the power generated under a 20-year power purchase agreement. The project anticipates the commencement of construction in late Q1 2012 with expected commercial operation achieved by the end of December 2012.
The agreement was finalised in November 2011. enXco will develop, build, and own the Spearville 3 Wind Project, consisting of 63 GE XLE turbines, while KCP&L will buy the power generated under a 20-year power purchase agreement. The project anticipates the commencement of construction in late Q1 2012 with expected commercial operation achieved by the end of December 2012.