The hook-up to the mooring lines which had been pre-laid in July 2017 was successfully executed by JIFMAR in the following days. A period of severe weather right after the floater’s installation (5 metres waves and 15 m/s wind speed) proved its sea keeping performance. The connection to the export cable and to the power grid will be scheduled in the very near future after a last series of tests.