GE Renewable Energy has announced that it has signed a Memorandum Of Understanding with Eolien Maritime France (EMF) confirming its commitment to provide and service Haliade 150-6MW turbines to the first French EMF offshore wind farm to be cleared of any legal recourse. This memorandum of understanding terminates GE's exclusive supplier status on the two other projects carried out by EMF.
The terms of the Memorandum of Understanding have not been made public. Currently, the three projects developed by EMF off Courseulles-sur-Mer, Saint-Nazaire and Fécamp are still awaiting the last court decisions, following appeals against the administrative authorisations required for their implementation. The cumulative excessive delays since 2012 on these projects, related to these claims, have significantly impacted the financial characteristics of those projects for GE Renewable Energy. GE has therefore decided to review its engagement in the implementation of all these projects.