The jacket foundation had been placed on site in October 2022. The installation involved the heaviest lifting operation for the Baltic Eagle project with a total estimated net weight of around 4,200 tonnes. Iberdrola now starts the offshore phase to make the OSS ready for energisation. This will be followed by the installation of the monopiles to which the wind turbines are attached with transition pieces.
Iberdrola completes installation of Baltic Eagle OSS topside