Latest Issue
 
Windtech International September October 2024 issue

 

FOLLOW US AT

follow

 

follow


Jan De Nul halfway through installation of 600 MW Kriegers Flak wind farmOn 27 January, Jan De Nul, Siemens Gamesa and Vattenfall installed the very first wind turbine for the Kriegers Flak offshore wind farm and Jan de Nul is now halfway. The last turbine is scheduled to be installed in mid-June.
 
The port of Roenne on the Danish island of Bornholm is serving as marshalling harbour for the construction of the offshore wind farm. The 72 wind turbines of 187 metres high will cover an offshore area of 132 km² at 15 to 40 kilometres off the Danish East coast. About 170 kilometres of subsea cables will be installed to connect the offshore wind farm to the Danish grid. The wind farm is expected to be fully operational by the end of 2021.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.