On 14 December 2016, A2SEA’s SEA INSTALLER completed the installation of 32 MHI Vestas 8MW turbines at DONG Energy’s Burbo Bank Extension in the Irish Sea.
This was the first time the 8MW turbines have been installed offshore and the installation was completed safely and in accordance with the installation plan. The wind farm has a total capacity of 258MW and is situated 7 km off the coast of Liverpool Bay. The wind farm is expected to be fully commissioned in Q1 2017.
A2SEA_Sea Installer_Burbo Bank Extension