Latest Issue
 
Windtech International September October 2024 issue

 

FOLLOW US AT

follow

 

follow


GeoSea has been awarded a contract for the transportation and installation of 90 wind turbine generators for the Triton Knoll Offshore Wind Farm in the UK. GeoSea will install 90 MHI Vestas 9.5 MW wind turbines at the 860MW wind farm located at the UK east coast.

GeoSea would be due to start work in Q1 2021. Its contract includes the design and manufacture of the sea-fastening and tagline systems, and the transportation and installation of all 90 of the 164 metre diameter turbines. The project is now progressing towards a financial investment decision likely in 2018 with full onshore construction starting shortly after, and offshore construction starting in 2020. First energy generation could be as early as mid-Q1 2021.

 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.