Mammoet was asked by Noatum Logistics, Saitec’s subcontractor, to transport and load-out the floater while fitted with a 2MW wind turbine. The floater was transported on SPMTs from its place of manufacture to the quay. Coordination was essential to ensure the availability of the seagoing vessel contractor coincided with appropriate tide levels and weather conditions. The project was carried out during two operations over one tide, so the barge was at the right level to load out the floater and offload the SPMT back onto the quay.