Effeventi has completed and submitted the
Environmental Impact Assessment of the wind farm and related electrical
projects to the Environment Ministry at the beginning of November 2005.
Since
then, Effeventi is going trough an intensive technical and administrative
process to comply with the all required concessions by law. This phase has also
involved the Ministry of Transports, the Ministry of Culture and somehow the
Region Molise, where the wind farm will be located. Effeventi obtained the
permits from the Environment Ministry? in
June 2008 and is expecting? to
receive? the marine / land concession
from the Ministry of Transports within September 2008.