The Nordex Group has secured an order in Spain with Delta4000 series turbines totalling 76.8 MW for an undisclosed customer. For an expansion phase of a wind farm in central Spain, the company will supply 16 N155/4.8 turbines.
The order also includes the service and maintenance of the turbines over two years. Delivery and installation of the first turbines will begin in August 2022, and commissioning is scheduled for December 2022. The Nordex Group will install the Delta4000 turbines on concrete towers with a hub height of 120 meters.