Bladt Industries has entered into a contract with Northwester for the delivery of a complete and fully installed substation to the forthcoming Belgian project Northwester 2 Offshore Wind Farm.
The contract is a turnkey contract (EPCI contract), which includes everything from design to final installation. With the overall responsibility for the entire project, Bladt has entered into a close cooperation with their long-term cooperation partners Semco Maritime, who will be responsible for the electrical systems and ISC Engineering, who are responsible for carrying out the structural design. The substation will be delivered in the third quarter of 2019. The substation is expected to have a total weight of 1,000 tons. The park will be installed in the Belgian part of the North Sea about 46 kilometres off the Belgian coast. The park will have a total of 224MW.