ODE has installed new pontoon and crane facilities on the Dudgeon Offshore Wind Farm base in Great Yarmouth. ODE designed, fabricated and installed a 52-metre long concrete pontoon system anchored by pilings in the river.
The £500,000 contract also saw ODE design, build and provide access and utilities to the crane loading area. The fully operational waterside marine facilities will be used by two to three crew transfer vessels, which will support construction, operations and maintenance work on the wind farm, 32 kilometres north of Cromer off the Norfolk coast. When completed, the Dudgeon Offshore Wind Farm will have a power generation capacity of 402MW.