Latest Issue
 
Windtech International September October 2024 issue

 

FOLLOW US AT

follow

 

follow


Ørsted has conditionally named Siemens Gamesa Renewable Energy as the preferred turbine supplier for two offshore wind power projects in the German North Sea totaling 1.142 GW.
 
At both the 900 MW Borkum Riffgrund 3 and the 242 MW Gode Wind 3 sites, Siemens Gamesa will deploy its new SG 11.0-200 DD offshore wind turbine. A five-year service and maintenance agreement is included in the preferred supplier award. The award is subject to certain conditions including Ørsted’s final investment decision, which itself is subject to the projects receiving final grid dates and final consents from German authorities. The final number of turbines for both projects remains to be determined. Ørsted expects the installation of Gode Wind 3 to begin in 2023, with commissioning being completed in 2024. The installation of Borkum Riffgrund 3 is expected to begin 2024, with commissioning being completed in 2025.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.