Vestas has received an 86MW order from Sacramento Municipal Utility District (SMUD) to repower the Solano Wind Project Phase 4 wind farm in California, USA.
The order consists of 19 V150-4.5MW wind turbines, which will replace the site’s current legacy V47-660 kW wind turbines. With this order, the collective Solano Wind Project will have a total capacity of about 300MW. The order includes a full Engineering Procurement Construction (EPC) contract. Vestas will provide a full turn-key solution with delivery, installation, and commissioning of the turbines. The order also includes a 10-year service agreement. Turbine delivery for Solano 4 begins in the fourth quarter of 2023 with commissioning scheduled for the second quarter of 2024.