The V164 platform was from the very beginning developed with a possible potential of increasing the turbine size. The progress in the technology development has now shown that an 8MW version will offer lower cost of energy and at the same time keep the reliability and structural integrity of the turbine unchanged.
The development of the new V164-8.0MW turbine is progressing according to schedule and several main components are close to completion.
The development of the new V164-8.0MW turbine is progressing according to schedule and several main components are close to completion.
- The blade mould for the 80-metre blades is ready at Vestas’ testing facilities on the Isle of Wight, UK, and the production of the first blade for testing purposes will be initiated during Q4.
- The prototype hub has been casted and is ready for testing.
- The generator and gear box will be ready for testing in Q1 2013.