OnPath Energy has appointed three key contractors for its six-turbine Mill Rig Wind Farm, located on the border of South Lanarkshire and East Ayrshire in Scotland.
Glasgow-based R J McLeod will deliver the balance of plant contract, covering civil engineering, cabling, and off-site highway construction. Nordex will supply and install six N163.5/X turbines, while energy consultancy Natural Power will oversee construction management.
Development work is expected to begin before Easter, with turbine deliveries planned for autumn. Construction and commissioning are scheduled for completion by spring 2026. The wind farm will have an installed generation capacity of approximately 33.4MW.