
The export cables will connect the offshore substation to the onshore substation using horizontal directional drilling (HDD). The cable installation will be carried out by cable-lay vessel Maersk Connector, which is on long-term charter to Seaway7. Execution of the scope will be led from Seaway7’s Taipei office in Taiwan. The project remains subject to final investment decision (FID).