Ilmatar has decided to construct the Korpilevonmäki wind farm located approximately 14 kilometers northeast of the center of Säkylä in South-West Finland.
The construction work of the 38.4MW wind farm will start immediately and planned commercial operation date is in the beginning of 2026. Korpilevonmäki wind farm consists of six wind turbine generators, which will be delivered, installed and commissioned by Vestas. The contract also includes a full scope service availability agreement for 30 years with possibility to extend up to 35 years. Ilmatar acquired the project rights for Korpilevonmäki in 2021. According to company’s strategy, the wind farm remains in Ilmatar’s ownership throughout its lifecycle. Enersense has been selected as the main contractor for the construction of the Korpilevonmäki wind farm infrastructure. Enersense’s delivery includes the construction of roads and lifting areas in the farm, turbine foundations and the internal network as a turnkey delivery.