Latest Issue
 
Windtech International November December 2024 issue

 

FOLLOW US AT

follow

 

follow


The installation of the 396MW Mareña Renovables project in Mexico has been delayed.
 
Vestas confirms that access to the project sites has continued to be impacted by minority opposition groups, which has caused significant delays in the construction of the project. Based on the delay, Mareña Renovables has entered into a forbearance agreement with the project lenders until 30 July 2013, which they expect to be extended subject to certain milestones being achieved; and with Vestas until 30 November 2013.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.