Ørsted has signed strategic volume contracts with Bladt Industries and Steelwind Nordenham who will be supplying monopile foundations for Ørsted's German offshore wind farms Gode Wind 3 (242MW) and Borkum Riffgrund 3 (900MW).
The two suppliers will be manufacturing a total of 107 monopile foundations for the German projects, including the foundation for the offshore substation for Gode Wind 3. Steelwind Nordenham will be supplying 66 monopiles, while Bladt Industries will be supplying 41 monopiles. In addition, Ørsted has secured call-off rights with Bladt and Steelwind for further volume for other projects, if needed. The monopiles for Borkum Riffgrund 3 and Gode Wind 3 will be up to 100 meters long, have a diameter of almost 10 meters, and weigh 1,200 tonnes or more. Subject to Ørsted's final investment decisions, Gode Wind 3 and Borkum Riffgrund 3 are expected to become fully operational by 2024 and 2025, respectively. Both projects will be powered by Siemens Gamesa's 11 MW offshore wind turbines.