Peikko Norge has received an order to supply rock foundation technology to the municipalities of Hå and Bjerkreim in Southern Norway. Peikko will deliver all steel components for the 70 foundations of the wind park.
The deliveries comprise Fatbar Rock Anchors, tower adapter plates, drilling templates and foundation reinforcement. Peikko is also responsible for the foundation design and structural calculations. Deliveries will start already in fall 2018. The wind park is estimated to be operational by the second half of 2019. Norsk Vind Energi AS, the developer of the wind park, executes the project on behalf of the German investor LUXCARA GmbH. Siemens Gamesa delivers 70 pieces of their SWT130-4.2 MW turbines with a hub height of 125 meters. Stangeland Maskin AS has been assigned for the civil work of the infrastructure including establishment of internal roads, hardstands, and preparation of the wind turbine location. Their subcontractor Backe Rogaland AS will perform the technical assembly of steel components and casting works of Peikko’s rock anchored foundations.