The Utility Regulator has signalled its intention to approve over GBP 44 million of investment to facilitate renewable wind generation.

The investment will increase the amount of renewable generation in the north and west of Northern Ireland that can access NIE’s transmission network. The investment package comprises:
  • GBP 26 million of capital expenditure to increase the capacity of the Tamnamore sub-station to accommodate renewable generation
  • GBP 2.6 million for upgrades to the Kells-Coleraine circuit; and
  • GBP 1.25 million for pre-construction costs for a third circuit between Omagh and Tamnamore with a further GBP 14.75 million earmarked for the completion of the capital works.
This investment should ensure that the network can accommodate 1000MW of renewable wind generation.  Currently, 451MW of wind generation is connected in Northern Ireland and a further 550MW has received planning permission.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.