Vestas has secured a conditional order agreement to supply 64 V235-15.0 MW wind turbines for EnBW’s 900 MW He Dreiht offshore wind project in 2025. In addition, Vestas will deliver a multi-year solution to service the wind project when operational.
Vestas has also entered a conditional agreement with Cadeler for the transportation and installation of the turbines for the He Dreiht project. Installation is planned to begin in the second quarter of 2025, with full park commissioning anticipated for the fourth quarter of the same year. The project has a grid connection capacity of 900 MW and an excess capacity of 60 MW in order to use the connection capacity as efficiently as possible even when production is lower. The V236-15.0 MW prototype development work is progressing across Vestas’ R&D and production sites, and the prototype wind turbine is planned for installation later this year, with serial production to begin from 2024.