Vestas has won a 63MW order to supply, install and commission 16 wind turbines for two projects in central Jutland in Denmark. The order is placed by Eurowind Energy.
Developed in collaboration with local partner Vindteam, the St. Soels project will comprise seven V126-3.45 MW turbines delivered in 3.6 MW Power Optimised Mode, while the Veddum Kær project will feature nine V136-4.2 MW turbines. As Eurowind Energy has developed both projects as co-located wind and solar power plants, the final energy output to the grid will consist of a hybrid mix. Turbine deliveries are expected to begin end of 2020 for the St. Soels project and in the second quarter of 2021 for the Veddum Kær project. Commissioning for St. Soels is planned for the first quarter 2021 and for Veddum Kær for the third quarter of 2021. The contract also includes a 20-year service agreement.