Vestas has received a 28MW repowering order from ecoJoule construct for the wind project Brest, located in Lower-Saxony in northern Germany, won in the tender for the Federal Network Agency.
Five V150-5.6 MW turbines from the EnVentus platform, with concrete hybrid towers with a hub height of 166m, will replace the currently installed turbines. The repowering doubles the project’s capacity. The contract includes supply, installation and commissioning of the wind turbines, as well as a 20-years service agreement. Deliveries are expected to begin in the second quarter of 2021, while commissioning is planned for the third quarter of 2021.