Latest Issue
 
Windtech International September October 2024 issue

 

FOLLOW US AT

follow

 

follow


Vestas has received an order for 269 MW of turbines, consisting of three V110-2.0 MW turbines, 22 V120-2.2 MW turbines, and 51 V150-4.2 MW turbines for a wind project in the U.S. Including previously purchased 2 MW platform components, the project has a total nameplate capacity of 299 MW.
 
The order includes supply and commissioning of the turbines as well as a 10-year service agreement. Turbine commissioning is scheduled for the fourth quarter of 2020. The project and customer are undisclosed.
 
Further Vestas has received an order for 183 MW of V120-2.2 MW turbines for a wind project in the U.S. with a number of turbines operating in 2.0 MW. Including previously purchased 2 MW platform components, the project has a total nameplate capacity of 202 MW. The order includes supply and commissioning of the turbines as well as a 10-year service agreement. Turbine delivery will begin in the second quarter of 2020 with commissioning scheduled for the fourth quarter of 2020. The project and customer are undisclosed.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.