European Energy and Novo Holdings have partnered to repower 17 operational wind farms in Germany. These wind farms, which became operational between 2002 and 2008, currently have a combined capacity of 151.9 MW.
This capacity is expected to more than triple following the repowering. The projects have secured most necessary rights and are in advanced stages of development. They are expected to achieve ready-to-build status between 2025 and 2027, and are forecast to become operational between 2027 and 2030.