The first of fifty wind turbines has been successfully installed at the 476MW Baltic Eagle offshore wind farm, a joint venture between Iberdrola and Abu Dhabi Future Energy Company – Masdar.
Collaborating with Vestas, the remaining wind turbines will be transported to the offshore construction site in the coming months and installed using the jack-up vessel Blue Tern, owned by Fred. Olsen Windcarrier. Baltic Eagle remains on track for operational readiness by the end of 2024. The offshore wind farm will generate green electricity from a total of 50 Vestas V174-9.5MW wind turbines, each with an output of 9.525MW.