GE and Göteborg Energi have started installing the first 4.1-113 Offshore Turbine in the Gothenburg harbour. This project marks the first commercial application of GE’s 4.1-113 technology, which was introduced in March 2011.
The turbine is located in Risholmsvägen, an area located at the harbour entrance. The nacelle, tower and blades will arrive by boat. The installation is planned to be finished by mid-December. The foundation, with a 21 meter diameter, is pile-driven into the rock. Completion of the installation and connection to the grid is planned for the end of this year.
The turbine is located in Risholmsvägen, an area located at the harbour entrance. The nacelle, tower and blades will arrive by boat. The installation is planned to be finished by mid-December. The foundation, with a 21 meter diameter, is pile-driven into the rock. Completion of the installation and connection to the grid is planned for the end of this year.