The last rotor of Ararat Wind Farm’s 75 turbines has been installed by contractor Mammoet. The cable trenching and installation by RJE Global is also completed. To finish the project there just remains the connection of cables to the turbines required to transport electricity generated to the substation and into the grid, commissioning of the remaining turbines and site rehabilitation.
61 of the 75 turbines are already commissioned and contributing to Victoria’s supply of renewable energy. The Ararat Wind Farm Pty Ltd is co-owned by a consortium of Renewable Energy Systems, GE, Partners Group on behalf of its clients, and OPTrust. The 240MW Ararat Wind Farm in south-west Victoria will be the third largest wind farm in Australia and has attracted almost half a billion dollars of direct international investment into Victoria.