Pattern Energy has started construction on its SunZia Transmission project. The Bureau of Land Management, U.S. Department of the Interior, has issued its Notice to Proceed, allowing construction to begin on SunZia.
U.S. Secretary of the Interior Deb Haaland joined senior elected and government officials to initiate the project’s groundbreaking at the SunZia East Converter Station in Corona, New Mexico.
SunZia Transmission is a 550-mile ± 525 kV high-voltage direct current (HVDC) transmission line between central New Mexico and south-central Arizona with the capacity to transport 3,000 MW of electricity across Western states. SunZia Transmission will deliver clean power generated by Pattern’s 3,500 MW SunZia Wind facility, which is being constructed across Torrance, Lincoln, and San Miguel Counties in New Mexico. SunZia Transmission will enable SunZia Wind to supply clean power to Western states when demand is high.