Triton Knoll has has unveiled MHI Vestas Offshore Wind as its preferred turbine supplier and its plans to use 90 of its 9.5MW turbines for its offshore wind farm.
Triton Knoll is a circa 860MW East coast offshore wind farm project and the project is now progressing towards a financial investment decision likely in 2018 with full onshore construction starting shortly after, and offshore construction starting in 2020. First energy generation could be as early as mid-2021, with the project expecting to begin commissioning in 2021.