In total, Van Oord will install approximately 70 kilometres of 66kV inter-array cables, manufactured by subcontractor TKF. To protect the cables, Van Oord will deploy its trencher Dig-It later this year to bury them.
This Tracked Remotely Operated Vehicle (TROV) drives unmanned over the seabed and creates a trench for the cables by liquefying the seabed. The 476MW Baltic Eagle offshore wind farm is located 30 kilometres northeast of the German island of Rügen and covers a 40 square kilometre area. It is scheduled to be fully operational by the end of 2024. Van Oord is responsible for the transport and installation of the wind turbine foundations and the supply, transport and installation of the inter-array cables.