Vestas has received a firm and unconditional order for 150 MW for several projects in Brazil from Energisa S.A.
The contract includes supply, installation and commissioning of the 75 2MW turbines, a VestasOnline Business SCADA system and a five-year Service Contract with the AOM 5000 solution. Delivery of the turbines is scheduled to start in Q1 2012, with completion estimated for December 2012.