Vestas has received a firm and unconditional order for two V126-3.3MW projects in Finland with a total capacity of 99MW from TuuliWatti Oy for the Kalajoki and Siikainen projects.
The order comprises delivery of 30 x V126-3.3 MW wind turbines together with a five-year AOM 5000 service agreement with an option for extension of up to ten years. Installation of the Kalajoki project will begin in the fourth quarter of 2014 with commissioning expected in the third quarter of 2015. Installation of the Siikainen project will begin in the third quarter of 2014 with commissioning expected in the first quarter of 2015.