Erciyas Çelik Boru A.?, has signed an agreement to construct a wind power plant using 16 V112-3.3MW wind turbines. The customer’s very first wind power plant will be ready for turbine installation in the first quarter of 2014.
The 52MW Kavakli RES wind power plant will be installed in the southern province of Balikesir in Turkey. The contract includes delivery, installation and commissioning of the wind power plant, including a five-year AOM4000 full scope availability agreement. The wind turbines for the Kavakli RES wind farm are scheduled to be delivered in the first quarter of 2014, with commissioning expected by the second quarter of 2014.