The first wind turbine at Grönhult wind farm is now being erected, where a total of twelve 5.6 MW wind turbines will be installed from Vestas. In May 2021, construction of the wind farm began.
The work began with the construction of roads and then parking spaces, foundations and the internal electricity network for the wind farm, which is located in Tranemo and Gislaved's municipalities. The park, which has a total installed capacity of 67.2 MW, will be put into operation at the end of the year. In February 2021, Grönhult was sold to the investment company TRIG, The Renewables Infrastructure Group Limited. Vattenfall Vindkraft is building the park and will during operation be responsible for the management of the wind farm.