Latest Issue
 
Windtech International September October 2024 issue

 

FOLLOW US AT

follow

 

follow


German transmission grid operator TransnetBW has commissioned Siemens to build new switchgear in the 380 kilovolt (kV) Daxlanden substation in Karlsruhe, Baden-Württemberg.
 
Two new gas-insulated indoor switchgear, initially with 26 panels, will boost the substation’s transmission capacity and cover the increased transport demand in the German high-voltage grid as a result of the transition to a new energy mix. In the future, it will thus be possible to transport large quantities of wind energy from northern Germany to the southern part of the country. Replacing sulfur hexafluoride (SF6) with treated air, so-called Clean Air, as the insulating medium in the bus ducts simultaneously ensures much more climate-friendly operation. The commissioning of the turnkey solution will take place in stages and be completed in 2029.
 
Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.