Natural Power has delivered technical advisory services for the 67.1 MW Benbrack wind farm, acting as lender’s technical advisor to support project financing on behalf of Red Rock Renewables.

 

Appointed to carry out a technical due diligence review, Natural Power provided lenders, including Lloyds, HSBC and China Construction Bank, with an assessment of the project’s technical, environmental and commercial readiness. This included evaluation of construction progress, turbine installation and commissioning, grid connection, and contractual arrangements.

The project has advanced through construction, with balance of plant works completed and turbine commissioning achieved. Grid connection was energised in September 2025, with final stages focused on takeover and the start of commercial operations.

In addition to core due diligence, Natural Power reviewed key risk areas such as turbine quality assurance, environmental and social management planning, and contractual frameworks including contracts for difference and power purchase agreements. The team also assessed the environmental and social management plan against Equator Principles requirements, confirming alignment with expected standards for a project of this scale and complexity.

Use of cookies

Windtech International wants to make your visit to our website as pleasant as possible. That is why we place cookies on your computer that remember your preferences. With anonymous information about your site use you also help us to improve the website. Of course we will ask for your permission first. Click Accept to use all functions of the Windtech International website.